logo
Copyright Vertimax Australia 2019
 

Rod Laver Arena – Roof Modernisation Works

About This Project

 

Vertimax Australia was engaged to complete the major upgrade works on the Rod Laver Arena moving roof during 2017 and 2018.

On completion the roof has been transformed from a 35-minute opening and closing time down to a 5-minute time frame. The goal was 8-minute timeframe.

The structural upgrades completed in 2018 saw the roof jacked up on purpose-built jacks and the eight new bogies lifted into position and the old bogies removed.

The project consisted of roof structural upgrades, bogie replacement, all motors and gearboxes, electrical switchboard and complete re-wiring. The contract also includes a full re-painting of the original roof structure.

Picture above taken on 22/5/2018 of the installation of the four western side bogies.

Location

Rod Laver Arena, Melbourne

Client

Lend Lease Construction

Project

Moving Roof Modernisation

Duration

2 Years – 2017-2018